This project will consist of filling all of the sidewalk gaps over the 2.6-mile stretch of Wrightsville Avenue from Independence Boulevard to Hawthorne Drive; completing ADA crosswalks along the route at cross streets; adding a signalized pedestrian crossing at College Road; and building a roundabout at the intersection of Wrightsville Avenue and Wallace Avenue. The roundabout will include new street lighting and a crosswalk.
A complete tree survey has been conducted to save healthy trees and minimize tree removals to the extent possible. The following priorities have guided the planning and design:
View a presentation to City Council from May 2020 about tree preservation efforts on this project here.
(PDF, 2MB)
Design on this project is complete. More than 70 property easements have been obtained and City Council has authorized staff to proceed with condemnation procedures for another 20-plus properties.
Once the city has obtained the necessary easements and/or property from these landowners, staff will be able to bid the job (advertise for a qualified construction contractor). Council will then vote to authorize award of the construction contract.
Prior to city contractor mobilization, the various utility companies will come on-site to relocate water, sewer, power and telecommunications lines along the 2.6-mile route.